Organics delivered a turnkey landfill gas power generation project for the IYO Alam Sekitar at the Bercham Landfill Site (LFS) in Ipoh, Malaysia.

Landfill gas contains methane, which is a highly potent greenhouse gas. This project was designed to control this critical environmental problem and convert the Landfill Gas (LFG) into a valuable, carbon-neutral resource. The system utilizes 2 x 500 kW spark ignition engines to safely remove LFG from the environment and convert it into much-needed electricity.

Project OVERVIEW

This 1 MWe LFG power generation project ensures that over 1,000 Nm3/hour of landfill gas is processed. The facility handles the gas, generates power, and displaces the use of fossil fuels for electricity generation in the region.

The project was executed as a turnkey solution, covering the design, fabrication, project management, installation, and commissioning of the entire system.

Project Specification

  • Waste Type: Landfill Gas (LFG)

  • Project Type: Turnkey Landfill Gas Power Plant

  • Biogas Potential (LFG flow): Over 1,000 Nm3/hour (~24,000 Nm3/day)

  • Total Power Capacity Installed: 1 MWe

  • Annual Electricity Potential: 7,000 MWh / year

  • Project Budget: USD 2 million

  • System Detail: 2 x 500 kW spark ignition engines

PROJECT Impact

  • Greenhouse Gas Emission Prevention: Captures LFG, preventing the release of high-GWP methane into the atmosphere, with an estimated capture of ~12,000 Nm3 of methane per day.

  • Carbon Equivalent Mitigation: Converts the captured methane into clean energy, achieving an estimated emission reduction of ~241 tonnes of CO2e per day.

  • Renewable Energy Generation: Generates 1 MWe of total installed power capacity, providing a stable, carbon-neutral electricity source.

  • Resource Conversion: Converts a major environmental liability into a resource, displacing the use of fossil fuels.

*Note (assumptions):

  • Methane Fraction: Methane content in the Landfill Gas (LFG) is assumed to be ~50%, which is typical for LFG projects.

  • GHG Reduction: Greenhouse Gas (GHG) reduction is calculated using the GWP100 for methane = 28 tCO2e per tonne of CH4.

  • Power Capacity: The electrical output of 1 MWe is based on the total power capacity installed.

Related Projects

Digester Biogas from Cassava Mill Effluent – PT CAM

Digester Biogas from Cassava Mill Effluent – PT CAM

Digester Biogas from Cassava Mill EffluentPT Cipta Agung Manis (CAM)Kendari, Southeast Sulawesi April 2015 - 2016PT Organics Bali completed the design, installation, and commissioning of a Closed Lagoon Bioreactor (CLBR) on the settling lagoon used for wastewater...

Digester Biogas from Cassava Mill Effluent – TEDCO

Digester Biogas from Cassava Mill Effluent – TEDCO

Digester Biogas from Cassava Mill EffluentPT TEDCO AGRI MAKMURSINARMAS AGROBandar Lampung, SumatraMarch 2015 - 2016PT Organics Bali completed the design, installation, and commissioning of a Closed Lagoon Bioreactor (CLBR) on the settling lagoon of the cassava mill...

POME Waste to Biogas for Co-firing – Sinarmas

POME Waste to Biogas for Co-firing – Sinarmas

Digester Biogas dari Palm Oil Mill Effluent (POME)PT SMARTSINARMAS AGROCentral KalimantanJune 2015 - 2016PT Organics Bali completed the design, installation, and commissioning of a Closed Lagoon Bioreactor (CLBR) system on the settling lagoon of a palm oil mill owned...

POME Waste to Biogas for Co-firing – PT Bumitama Gunajaya Agro

POME Waste to Biogas for Co-firing – PT Bumitama Gunajaya Agro

Digester Biogas dari Palm Oil Mill Effluent (POME)PT BUMITAMA GUNAJAYA AGROPT Karya MakmurMahagiaCentral KalimantanAugust 2024 - 2025PT Organicsindo Konstruksi Energi (Organics Bali) has completed the development of a POME-to-Power biogas system for Gunung Makmur...

POME Waste to Biogas for Power – PT EVANS

POME Waste to Biogas for Power – PT EVANS

Digester Biogas dari Palm Oil Mill Effluent (pome)PT EVANSPT Bumi Mas AgroEast KalimantanMarch 2020 - 2021The project was for the design, installation, and commissioning of a Closed Lagoon Bio-Reactor (CLBR) for the treatment of palm oil mill effluent (POME). The...

Work With Experts in Waste to Energy Project – Contact Us Now!

organics

PT ORGANICS BALI

CONTACT US

Head Office

Rukan Exclusive Blok G No.35

Jl. Pantai Indah Kapuk Jakarta Utara

(021) 55965958

Engineering Office

Setrasarimall Ruko B3/83

Jl Surya Sumantri No 44, Bandung

(022) 20285549

ORGANICS GROUP

Data Privacy and Protection Policy

Organics Privacy Policy

Updated June 2025

Translate »